Project Management For Managers Assignment 8 Answers 2021

Project Management Assignment 8 Answers:- Every student is requested to submit their assignments on the knowledge of their own, we do not promote copying answers. We are providing answers just as a reference.

Q1. Which one is not an MCDM technique?

(A) AHP 

(B) VIKOR 

(C) PERT  

(D) TOPSIS

Ans:- (C) PERT  

Q2. An activity has an optimistic time 15 days, a most likely time of 18 days, and a pessimistic time 27 days. What is its expected time? 

(A) 18 days 

(B) 19 days 

(C) 20 days 

(D) 21 days

Ans:- (B) 19 days 

ALSO READNPTEL – Online Courses,Certificate And full details

Q3. PERT analysis is based on  

(A) Pessimistic time estimate 

(B) Optimistic time estimate 

(C) Most likely time estimate 

(D) All of the above

 Ans:- (D) All of the above

Q4. A project’s critical path is composed of activities A, B and C.  Activity A has standard deviation of 2, activity B has a standard deviation of 1, and activity C has a standard deviation of 2. What is the standard deviation of the critical path?

(A) 9 

(B) 5 

(C) 3 

(D) 25

Ans:- (C) 3 

Q5. Slack time refers to 

(A) An activity 

(B) An event 

(C) Both event and activity 

(D) None of the above 

Ans:- (B) An event 

Q6. Four experts A, B, C, D examined an activity and arrived at the following time estimates. Determine which expert is more certain about his estimates of time:

Experts     Time Estimate    

to    tm    tp

A    4    6    8

B    4    7   10

C    5    8   12

D    4    7   11

(A) A

(B) B

(C) C

(D) D

Ans:- (A) A

Questions 7 to 10 are linked questions use given data (use normal probability distribution table for appropriate question, you can refer to video for table or other resources). A project consists of seven activities with the following time estimates.

ActivityPredecessor
Activity
Optimistic time
estimate (to)
Most likely time
estimate ™
Pessimistic Time
estimate ( tp)
A258
BA234
CA6810
DA246
EB2610
FC678
GD,E,F6810

Q7. Determine the critical path of the project 

(A) 1-2-3-5-6 

(B) 1-2-4-5-6 

(C) 1-2-5-6 

(D) Inefficient data provided

Ans:- (B) 1-2-4-5-6 

Q8. Find out the time required to complete the project. 

(A) 22 weeks 

(B) 28 weeks 

(C) 17 weeks 

(D) None of the above

Ans:- (B) 28 weeks

Q9. Find out the standard deviation of the project. 

(A) 1.414 

(B) 2.414 

(C) 1.69 

(D) 2.25

Ans:- (A) 1.414 

Q10. Find the probability that the project will be completed in 30 week or less.  

(A) 0.92 

(B) 0.65 

(C) 0.95 

(D) 0.98

Ans:- (A) 0.92 