Q1. Which one is not an MCDM technique?
(A) AHP
(B) VIKOR
(C) PERT
(D) TOPSIS
Ans:- (C) PERT
Q2. An activity has an optimistic time 15 days, a most likely time of 18 days, and a pessimistic time 27 days. What is its expected time?
(A) 18 days
(B) 19 days
(C) 20 days
(D) 21 days
Ans:- (B) 19 days
ALSO READ : NPTEL – Online Courses,Certificate And full details
Q3. PERT analysis is based on
(A) Pessimistic time estimate
(B) Optimistic time estimate
(C) Most likely time estimate
(D) All of the above
Ans:- (D) All of the above
Q4. A project’s critical path is composed of activities A, B and C. Activity A has standard deviation of 2, activity B has a standard deviation of 1, and activity C has a standard deviation of 2. What is the standard deviation of the critical path?
(A) 9
(B) 5
(C) 3
(D) 25
Ans:- (C) 3
Q5. Slack time refers to
(A) An activity
(B) An event
(C) Both event and activity
(D) None of the above
Ans:- (B) An event
Q6. Four experts A, B, C, D examined an activity and arrived at the following time estimates. Determine which expert is more certain about his estimates of time:
Experts Time Estimate
to tm tp
A 4 6 8
B 4 7 10
C 5 8 12
D 4 7 11
(A) A
(B) B
(C) C
(D) D
Ans:- (A) A
Questions 7 to 10 are linked questions use given data (use normal probability distribution table for appropriate question, you can refer to video for table or other resources). A project consists of seven activities with the following time estimates.
Activity | Predecessor Activity | Optimistic time estimate (to) | Most likely time estimate ™ | Pessimistic Time estimate ( tp) |
A | – | 2 | 5 | 8 |
B | A | 2 | 3 | 4 |
C | A | 6 | 8 | 10 |
D | A | 2 | 4 | 6 |
E | B | 2 | 6 | 10 |
F | C | 6 | 7 | 8 |
G | D,E,F | 6 | 8 | 10 |
Q7. Determine the critical path of the project
(A) 1-2-3-5-6
(B) 1-2-4-5-6
(C) 1-2-5-6
(D) Inefficient data provided
Ans:- (B) 1-2-4-5-6
Q8. Find out the time required to complete the project.
(A) 22 weeks
(B) 28 weeks
(C) 17 weeks
(D) None of the above
Ans:- (B) 28 weeks
Q9. Find out the standard deviation of the project.
(A) 1.414
(B) 2.414
(C) 1.69
(D) 2.25
Ans:- (A) 1.414
Q10. Find the probability that the project will be completed in 30 week or less.
(A) 0.92
(B) 0.65
(C) 0.95
(D) 0.98
Ans:- (A) 0.92
NPTEL ALL WEEK ASSIGNMENT ANSWERS:-
- Soft Skill Assignment Answers
- Project Management For Managers Answer
- Semiconducter Devices And Circuit Answer
- Problem Solving Through Programming In C Answer
Project Management Assignment 8 Answers:- Every student is requested to submit their assignments on the knowledge of their own, we do not promote copying answers. We are providing answers just as a reference.