Q1. The particular task performance in CPM is known
(A) Dummy
(B) Event
(C) Activity
(D) Contract
Ans:- (C) Activity
Q2. Network of a project is constructed based on
(A) Critical path
(C) Normal time and Crash Time
(C) Precedence Logic
(D) Basic Logic
Ans:- (C) Precedence Logic
Q3. In CPM network critical path denotes the
(A) Path where maximum resources are used
(B) Path where minimum resources are used
(C) Path where delay of one activity prolongs the duration of completion of project
(D) Path that gets monitored automatically
Ans:- (C) Path where delay of one activity prolongs the duration of completion of project
Q4. For an activity in a CPM analysis, the early Finish time is 13 and the late Finish time is 13. Duration of activity is 6. Which of the following statements is true?
(A) The early start is 6
(B) The duration of the activity is 13
(C) The slack of this activity is 13
(D) The activity is on the critical path
Ans:- (D) The activity is on the critical path
Q5. In the time-cost optimization, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having
(A) Longest duration
(B) Highest cost slope
(C) Least cost slope
(D) Shortest duration
Ans:- (C) Least cost slope
Q6. The reduction in project time normally results in
(A) decreasing the direct cost and increasing indirect cost
(B) increasing the direct cost and decreasing the indirect cost
(C) increasing both direct and indirect cost
(D) decreasing both direct and indirect cost
Ans:- (B) increasing the direct cost and decreasing the indirect cost
Q7. An act (i,j) as critical if and only if
(A) Total float = 0
(B) Free float = 0
(C) Independent float = 0
(D) All of the above
Ans:- (D) All of the above
Q8. In Project crashing, rent and overheads are treated as
(A) Significant Cost
(B) Insignificant costs
(C) Direct Costs
(D) Indirect Costs
Ans:- (D) Indirect Costs
Q9. Assertion (A): The change in critical path required rescheduling in a PERT network.Reason (R): Some of the activities cannot be completed in time due to unexpected breakdown of equipment’s or non-availability of raw materials.
(A) Both A and R are individually true and R is the correct explanation of A
(B) Both A and R are individually true but R is not the correct explanation of A
(C) A is true but R is false
(D) A is false but R is true
Ans:- (B) Both A and R are individually true but R is not the correct explanation of A
Q10. In a construction project, the cost-slope of an activity is an indication of
(A) Extra-time needed
(B) Extra cost needed
(C) Reduction of duration of critical activity
(D) Crashing of an activity
Ans:- (B) Extra cost needed
NPTEL ALL WEEK ASSIGNMENT ANSWERS:-
- Soft Skill Assignment Answers
- Project Management For Managers Answer
- Semiconducter Devices And Circuit Answer
- Problem Solving Through Programming In C Answer
Project Management Assignment 10 Answers:- Every student is requested to submit their assignments on the knowledge of their own, we do not promote copying answers. We are providing answers just as a reference.