Q1. The particular task performance in CPM is known 

(A) Dummy  

(B) Event  

(C) Activity  

(D) Contract

Ans:- (C) Activity  

Q2. Network of a project is constructed based on  

(A) Critical path 

(C) Normal time and Crash Time 

(C) Precedence Logic 

(D) Basic Logic

Ans:- (C) Precedence Logic 

Q3. In CPM network critical path denotes the 

(A) Path where maximum resources are used 

(B) Path where minimum resources are used 

(C) Path where delay of one activity prolongs the duration of completion of project 

(D) Path that gets monitored automatically

Ans:- (C) Path where delay of one activity prolongs the duration of completion of project 

Q4. For an activity in a CPM analysis, the early Finish time is 13 and the late Finish time is 13. Duration of activity is 6. Which of the following statements is true?  

(A) The early start is 6 

(B) The duration of the activity is 13 

(C) The slack of this activity is 13 

(D) The activity is on the critical path

Ans:- (D) The activity is on the critical path

Q5. In the time-cost optimization, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having 

(A) Longest duration 

(B) Highest cost slope 

(C) Least cost slope 

(D) Shortest duration

Ans:- (C) Least cost slope 

Q6. The reduction in project time normally results in 

(A) decreasing the direct cost and increasing indirect cost 

(B) increasing the direct cost and decreasing the indirect cost 

(C) increasing both direct and indirect cost 

(D) decreasing both direct and indirect cost 

Ans:- (B) increasing the direct cost and decreasing the indirect cost 

Q7. An act (i,j) as critical if and only if  

(A) Total float = 0 

(B) Free float = 0  

(C) Independent float = 0 

(D) All of the above 

Ans:- (D) All of the above 

Q8. In Project crashing, rent and overheads are treated as 

(A) Significant Cost  

(B) Insignificant costs  

(C) Direct Costs  

(D) Indirect Costs 

Ans:- (D) Indirect Costs 

Q9. Assertion (A): The change in critical path required rescheduling in a PERT network.Reason (R): Some of the activities cannot be completed in time due to unexpected breakdown of equipment’s or non-availability of raw materials. 

(A) Both A and R are individually true and R is the correct explanation of A 

(B) Both A and R are individually true but R is not the correct explanation of A 

(C) A is true but R is false 

(D) A is false but R is true

Ans:- (B) Both A and R are individually true but R is not the correct explanation of A 

Q10. In a construction project, the cost-slope of an activity is an indication of 

(A) Extra-time needed 

(B) Extra cost needed 

(C) Reduction of duration of critical activity 

(D) Crashing of an activity

Ans:- (B) Extra cost needed 